a. The project scope management plan describes and documents a scope baseline to help make future project decisions.
b. The project scope management plan decomposes project deliverables into smaller units of work.
c. The project scope management plan describes how project scope will be developed and
how changes will be managed.
d. The project scope management plan describes how cost and time estimates will be developed for project scope changes.
and the answer is.....
C. Reason?
The scope management plan outlines how project scope will be managed and how changes will be incorporated into the project.